750 kv substation construction, support part performance table

Release time:2019-04-06 13:05   Article From:未知   visits:

The serial number

The owner unit

The project name

Voltage level (kV

The product type

The number of

(t)

The contract signing date

Delivery time

Commissioning time

The owner unit references

Contact phone number

Whether the user operation

1

electricity transmission &transformation facilities engineering company in sichuan

750kVTransmission line project

750kV

Architecture and pillar

631.80

2010.12.02

 2011-3-17

 2011-5-20

Li wei,

028-65053764

yes

2

electricity transmission &transformation facilities of shandong company

xining750kVSubstation reconstruction project

750kV

Architecture support

512.853

2012.11.13

2013-3-7

2013-6-11

Sun Xueping

0531-82167568

yes